Wakefield progress meeting
Bulk excavation is held by the drainage connection, not by weather or resource. The 20T excavator comes off hire this week regardless. The phase end date moves once the authority responds, and not before.
Decisions
- The 20T excavator is off-hired on Friday whether or not the dig restarts — standing time is no longer justifiable at £420/week.
- The eastern edge is re-profiled to a shallower batter rather than sheet-piled; piling was priced at four weeks and the programme cannot absorb it.
- No revised phase end date is issued to the client until the drainage authority confirms in writing.
Actions
- Ruth Pilling 20 Aug Escalate the drainage connection to the authority’s regional office in writing
- Barry Thackeray 22 Aug Off-hire the 20T excavator and confirm collection
- Adam Verity 26 Aug Re-price the eastern edge as a re-profile and issue to Graham
- Graham Whitmore ongoing Hold the revised programme until the authority responds
Present Barry Thackeray · Graham Whitmore · Ruth Pilling · Adam Verity