Bradford Riverside Apartments — Plot 5
Riverside apartment block, podium slab
Generated from confirmed Work Records only. Deterministic query — same plot, same result, every time. Unconfirmed entries excluded from the evidentiary body.
Work Record Trail
| Date | Work Type | Description | Operative | Certification | Plant Used |
|---|---|---|---|---|---|
| 2026-07-28 | Setting Out | Podium slab set out to drawing 4102-C, levels checked against site datum. | Wes Duffield | CSCS Gold | — |
| 2026-07-30 | Reinforcement | Bottom mat fixed and tied, B785 mesh with T16 edge trimmers, cover checked at 40mm. | Marek Sowa | CSCS Blue · Steelfixer | — |
| 2026-08-03 | Formwork | Perimeter shutters erected and propped to podium edge, line and level signed off before pour. | Wes Duffield | CSCS Gold | Telehandler 4T |
| 2026-08-06 | Concrete Pour | Podium slab poured, C32/40, 46m³ placed and vibrated. Cube samples taken at 14m³ and 38m³. | Dermot Cassidy | CPCS Concrete Pump | Concrete Pump 32m |
| 2026-08-12 | Finishing | Power float completed, surface regularity checked to SR2. Curing membrane applied same day. | Marek Sowa | CSCS Blue · Steelfixer | Power Float |
| 2026-08-14 | Sign-off | Podium slab to Plot 5 complete and inspected. Cube results at 28 days to follow under separate cover. Plot released for handover. | Ian Sagar | SMSTS · Site Manager | — |
Detail
28 Jul 2026 — Setting Out
Podium slab set out to drawing 4102-C, levels checked against site datum. — carried out by Wes Duffield (CSCS Gold) , verified by Ian Sagar at 2026-07-28 16:42.
Source: Voice note · Confirmed: 2026-07-28 16:42
30 Jul 2026 — Reinforcement
Bottom mat fixed and tied, B785 mesh with T16 edge trimmers, cover checked at 40mm. — carried out by Marek Sowa (CSCS Blue · Steelfixer) , verified by Ian Sagar at 2026-07-30 17:05.
Source: Voice note · Confirmed: 2026-07-30 17:05
3 Aug 2026 — Formwork
Perimeter shutters erected and propped to podium edge, line and level signed off before pour. — carried out by Wes Duffield (CSCS Gold) , using Telehandler 4T, verified by Ian Sagar at 2026-08-03 15:20.
Source: Photo · Confirmed: 2026-08-03 15:20
Photo evidence — Formwork, Plot 5, 3 Aug 2026
…and 3 more records
Sign-Off
Podium slab to Plot 5 complete and inspected. Cube results at 28 days to follow under separate cover. Plot released for handover.
Verified by Ian Sagar (SMSTS · Site Manager) · 14 Aug 2026
Report generated 14 Aug 2026 · Source: confirmed Work Records, joined against roster reference data at generation time · Cuprix