West YorkshireCircle size = operatives on site
Wakefield Distribution Hub
DELAYEDBarry Thackerayforeman
14on site
£2,464hire overrun
Bulk Excavation · 23 days past phase end
Open Wakefield Distribution Hub in the live workspace
Kirkstall Retail Park
AT RISKDanny Ogdenforeman
12on site
£361hire overrun
Groundworks & Foundations · 7 days past phase end
Open Kirkstall Retail Park in the live workspace
Huddersfield New Build
ON PROGRAMMENeil Crossleyforeman
18on site
£1,820hire overrun
Foundations & Groundworks · 54 days of phase remaining
Open Huddersfield New Build in the live workspace
Bradford Riverside Apartments
ON PROGRAMMEIan Sagarforeman
17on site
—no overrun
Frame & Slabs · 84 days of phase remaining
Open Bradford Riverside Apartments in the live workspace
Halifax Industrial Estate
ON PROGRAMMEKeith Amblerforeman
9on site
—no overrun
Groundworks & Drainage · 24 days of phase remaining
Open Halifax Industrial Estate in the live workspace