Today, 10:22
Got it. Here's what I picked up:
• Concrete pour started on time, pump working fine
• Second ready-mix load running about 20 minutes behind
• Keeping plant off the southern end — ground still soft
Anything to correct?
10:23
Today, 15:04
Got it. Here's what I picked up:
• Slab poured and finished on ground floor — no issues
• West gable blockwork behind, lost time waiting on access during the pour
• 6 courses done, 3 short of what was planned for today
Anything to correct?
15:05
The 3 short — that's because of the access, not the lads. Make sure that's clear.
15:07
Updated: west gable 3 courses behind due to access delay during pour, not a labour issue. ✓ Logged.
15:07